Bro Tathan Large Scale Power

PROJECT SCOPE

Burroughs were appointed to assist Welsh Government in securing a new power supply for the new Bro Tathan Development. The project faced grid constraints and a challenging power supply landscape, the decision to establish an independent power supply became a strategic imperative to enhance the site’s appeal to potential developers.

Burroughs played a pivotal role in securing a crucial application to the National Grid Electricity Transmission, the authority responsible for England and Wales’ high-voltage electricity network, spearheading the approval for a significant power supply via the 132kV network.

This project demonstrates Burroughs’ commitment to delivering innovative solutions that drive progress and meet the unique challenges of each project.